Wednesday, 3 June 2009

Progress on all fronts

It's been a busy few days at Hillside. Over the weekend we completed installation of the recycled insulation. We also found time to dig over the first bit of the veg plot and setup hazel sticks to grow the runner beans and mangetout up.

Ths builder and plumber have been busy installing plasterboard, the new double glazed timber windows, the boiler and yesterday they finally dropped the rainwater tank into place. With quite a few guys onsite it's great to see things coming together.

And even though it's a little premature, the kitchen island was delivered yesterday, but that gives us time to sand it down and give it the restoration it needs.

Busy all round...hence the brief general update!